No More Delayed Projects ?
Prime Minister Modi Asks For Dossiers On Delayed Projects To Fix Responsibility / Swarajya / 26 Aug 2021
Extract :
Prime Minister Narendra Modi has directed the Cabinet Secretary to prepare "dossiers" of delayed projects within one week and identify the officers and agencies responsible for the delays.
Dear Narendrabhai,
I hope those “ dossiers “ help you in fixing the responsibility of delays on specific officers – and take appropriate actions ( stagnation – transfer – demotion – dismissal ? )
But then, you just won’t have time to read hundreds of dossiers ( one for each delayed project )
In fact, this ( preparation and review of dossiers by you ) should NOT even be necessary, if the following suggestion ( which I have been e-mailing to all Cabinet Minister for past 6 YEARS ) gets implemented :
Simply enable millions of citizen to openly VIEW on some website, PERT charts for each and every Infra project, which clearly highlights, dynamically / every day :
Ø Amount of “ Time-Delay “ and “ Cost Over-run “ , as compared to the targets
Ø Name of the Officer responsible ( along with his Mobile No / Email ID ) for each ACTIVITY on PERT
PERT technique was introduced in USA, some 60 years ago
Today, India’s software geeks are capable of :
Ø Developing a much superior technique ( with DELAY-ALERTS being delivered on Mobiles )
Ø Punishment / Promotion of concerned officers, as outlined at :
Artificial Intelligence to fix MP / MLA Salary ?................ [ 22 Feb 2018 ]
Let the entire process be available for REVIEW by citizen in an open / transparent manner
Things will improve dramatically
With regards,
Hemen Parekh / hcp@RecruitGuru.com / 27 Aug 2021
==============================
Nothing prettier than PERT ! …………………………………………………. [ 04 Dec 2015 ]
Extract :
My suggestions :
* When any Ministry submits any Project Proposal for Cabinet approval , it must be accompanied by a PERT
Program Evaluation and Review Technique ) chart , clearly showing all the " Activities " lying along
the CRITICAL PATH ( earlier known as the CRITICAL PATH METHOD )
That PERT Chart must accompany a tabulation showing , for each " Activity ",
# “ Pessimistic Time “
# “ Optimistic Time “ , and the
# “ Most likely Time “
Since Admiral Rickover , introduced this mandatory requirement for awarding tender to build the first
nuclear submarine, some 50 years ago , all US government departments follow this procedure for all govt
contracts
* Insist that all the government departments / contractors, responsible for execution of any of these
"activities", update the PERT chart status online on the web site of the Project Monitoring Group
* PERT charts for all the projects should be made visible to the general public
* If there is any " slippage " in any activity lying on the CRITICAL PATH , the name of the department
or contractor responsible , must appear in bold RED letters , against that activity
This is the only INNOVATION that we need , to ensure that the projects get completed in time and within
budget
Remembering Admiral Rickover ! ………………………………………….[ 04 June 2017 ]
Extract :
Decades ago , Admiral Rickover ( US Navy ) introduced the concept of PERT and insisted that all future bids ( for Navy Contracts ) be accompanied by a PERT chart
If Defence Acquisition Council wants to ensure that this procurement does not meet the fate of many of our earlier attempts to develop indigenous technologies , where a 4 year project went on for 24 years , then DAC should seriously consider my following suggestion ( earlier sent as email to all Policy Makers )
PERT for Digital Dashboard……………………………………………………. [ 27Feb 2018 ]
Extract :
Very soon, the Chief Minister will be able to monitor the status of all development projects in the state, in real-time, on his mobile, laptop and other digital platforms via a digital dashboard.
The State Directorate of Information Technology has been working on an electronic interface that aggregates and visualizes data from multiple sources.
In the second phase, members of the public can access a portion of the live dashboard, giving the workings of the projects transparency.
The digital dashboard will also help the CM fix loopholes, curb scams and anticipate and lift roadblocks.
My Suggestion :
If this “ digital dashboard “ has to become an instrument for fixing accountability of officers / agencies responsible for project delays , then I urge Shri Fadnavisji to employ project planning and review technique described in my following blog
==============================
Monitoring Projects in Real-time ? …………………………………………..[ 11 Aug 2020 ]
Extract :
After a long wait , this suggestion seems to be on the verge of “ acceptance “
Suggestion :
Ø Getting all Infrastructure Projects Status updated in real time
Ø Enabling “ Distributed Updating “ of Project Status by different Ministries / Agencies
Ø Allowing all citizen to view latest status of any project, online on a Govt website
What tells you this might happen ?
Following news report in today’s Business Line ( 11 Aug 2020 ) :
Finance Minister launches online dashboard for National Infra Pipeline