Dear Amitabh ,
Economic Times ( 05 May ) talks about a PMO letter to NITI Aayog , as follows :
" NITI Aayog is requested to undertake monthly monitoring of the implementation of
decisions taken, create a dashboard for
constant Monitoring, Evaluation and Review, and fix up outcome
targets for all major schemes of infrastructure and social sectors for
FY2016-17 and submit them to PMO by May 21, 2016 "
Allow me to reproduce below, my earlier email ( dt 05 Dec
2015 ) :
Nothing Prettier
than PERT !
Economic
Times ( 12 Oct 2015 ) carries a report
titled :
"
Panel set up for Innovation in Govt Projects
"
As
per this report, the Prime Minister has put together a team that will decide,
--
how government projects can be executed using cutting edge technologies and
practices
The
empowered committee for Innovative Collaborations was set up to incorporate the
very latest solutions that science and technology has to offer
MY SUGGESTION :
*
When any Ministry submits any Project Proposal for Cabinet approval , it MUST
be accompanied by a PERT ( Program Evaluation and Review Technique )
Chart , clearly showing all the " Activities " lying along the
CRITICAL PATH
-
( earlier known as the CRITICAL PATH METHOD
)
That PERT Chart must accompany a tabulation showing , for each " Activity
",
# Pessimistic Time
# Optimistic Time , and the
# Most likely Time
Since Admiral Rickover , introduced this mandatory requirement for awarding
tender to build the first nuclear submarine, some 50 years ago , all US
government departments follow this procedure for all govt contracts
*
Insist that all the government departments / contractors, responsible for
execution of any of these "activities", update the PERT chart status online on the web site of the Project
Monitoring Group , on a DAILY basis
*
PERT charts for all the projects should be made visible
to the general public
*
If there is any " slippage " in any activity lying on the CRITICAL PATH
, the name of the department or contractor responsible , must appear in bold
RED letters , against that activity
This
is the only INNOVATION that we need to
ensure that the projects get completed in time and within budget
-------------------------------------------------------------------------------------------------------------------------
As
you would have noticed in my suggestion , the best results would be achieved ,
when department / ministry proposing the project is , itself made responsible for :
#
Preparing a comprehensive list of Project
Activities and their " sequences " ( parallel or consequential
)
#
Estimating " Time " , each
activity will take to complete
#
Defining ( by name / designation / mobile number /
email ID ) , those responsible for each activity
#
Uploading all of these DATA , in the PERT INPUT
page on web site of NITI Aayog
#
Update the PERT CHART on daily basis
Entire idea is to put the ball in the court of these
departments / ministries !
If
created / maintained by NITI Aayog , the chart ( Dashboard ) would become an
instrument of endless arguments !
Wishing
you luck,
with
regards,
hemen
parekh
Marol
, Mumbai , India