Ms Jayshree Mahajan / Shri Dharmendra
Songira / Shri Ajit Desai
Bhoomi Green CHS Ltd , Borivli ( East )
Dear Friends ,
At the outset , congratulations
on installing a Solar Roof Top plant in your
society
I read about it in yesterday’s Hindustan Times and
sent to you following link through your web site :
I got following highlights ( of your installation )
from the news report :
·
System
consists of 256 solar panels on 3 buildings ( 74 Kwp )
·
Was
installed within ONE MONTH
·
Helped
by : Saur Engineers Consultants Private Limited
·
Total
cost of installation = Rs 47 lakhs
·
Total
Subsidy from Maharashtra Government = Rs 12.81 lakhs ( @ Rs 18,300 / Kwp )
·
You
expect to recover the cost (entire Rs 47 lakhs ? ) over 4 years
·
System
is registered in National Data Repository ( MNRE’s National Solar Mission )
·
A
net-metering system is installed to enable surplus power to be fed back into
the grid
·
Power
Supplier ( DISCOM ) will charge the Society , only at the end of the year for “
net usage “
·
Society
will save Rs 97,000 / month ( Rs 11.7 lakhs / year )
·
Estimated
solar electricity generated / day = Between 240 – 274 Kwh
·
MNRE estimate :
#
Ave 2 BHK flat in Mumbai , needs 10-12 Kwh of
electricity
# A 74 Kwp system can help save over 2276
tons of carbon being released over 10
years
# Saving in carbon emission is
equivalent to planting 3641 full-grown teak trees
Apparently ,
your Society raised Rs 34 lakhs ( Rs 47
lakhs – Rs 13 lakhs of subsidy )
At 10 %
interest , that would cost you , Rs 3.4 lakhs /
year ( say , Rs 30,000 / month )
But , if
that fund of Rs 34 lakhs was “ interest free
“ , then how much less would that power cost ?
To get a
glimpse , you may want to look up :
With Regards,
hemen
parekh / Andheri / Mumbai
(
M ) +91 - 98,67,55,08,08
Cc
: Go Green Ventures – Thane ( with a request to forward this mail
to Smt Sushma Goregaonkar of Hill Crest Society – Thane )
No comments:
Post a Comment