A HALF-WAY HOUSE ?


A   HALF-WAY   HOUSE   ?
On 02 Jan 2016 , Maharashtra CM , Shri Fadnavis released , " Construction Permit Guidelines Manual ", incorporating following reforms :
*  No of approvals.......... Down from 119 to 58
*  Time required............  Down from 365 days to 60 days
*  Approval Layers...........From multiple stages to single stage
*  Scrutiny Stages........... From multiple levels to only 2 parts
*  Process.....................  Parallel instead of serial
*  Payments..................  From 89 stages to 1 stage / online
*  Certifications.............   From BMC to self certification ( for certain services )
                                       From BMC to Consultants ( for certain services )

Congratulations , Shri Fadnavis-ji  . No doubt , a good beginning
But treat this as a  half way house
This won't help you to build those 5 lakh houses by 2020  !
Only implementation of my following blog that I sent to you on 5th Nov 2015 , will :
------------------------------------------------------------------------------------------
SELF   CERTIFICATION  FOR  BUILDERS  ?

In Hindustan Times ( Oct 29 ) , Moushumi Das Gupta writes :
Govt to streamline rules for Construction Projects
Currently , a builder requires as many as 34 kinds of permits from two dozen Ministries, before starting construction
This process takes up to 3 years
Now, Central Govt has initiated a process to streamline the approvals required to ensure that builders get all the construction permits within 60 days
Eg:
*    Built up Area............. Environment Ministry
*    Height Restriction...... .Civil Aviation Ministry
Cabinet Secretary has directed all the Ministries to come out with notifications by end Dec 2015
The Centre has decided to empower Municipalities to grant all construction related approvals , based on these notifications
One would be able to get all approvals from under one roof , which in this case , would be the Municipal Corporation's office
Although a very laudable initiative , I believe there is tremendous scope to further streamline and digitize this approval process, in the nature of
E-Delivery of Services to Construction Industry
Here is how :
*  All builders / developers must register on Municipal Web sites and obtain
   unique BUILDER REGISTRATION NUMBER
*  Builders must fill in online, on web site of concerned Municipality, a form :
    BUILDING  PERMIT  APPLICATION 
*  Building Permit Application Form will have a STANDARD FORMAT , into
    which applicant will need to submit exhaustive details re the project
    This will include detailed Floor Plans and Structural Drawings , along with
    names / contact details of Architects / Structural Engineers etc
    The FORM will require slab-casting dates for each slab and the final
    completion date when builder will apply for Occupation Certificate
   
*  The Form will have a section called
    SELF   CERTIFICATION   /  DECLARATION
    Builder would be required to tick YES / NO against each item as shown :
    Does your proposed Building / Structure / Project , satisfy the criteria /
    notifications / regulations , issued by the concerned Ministries in respect
    of :
    #   Built-up Area........... ( YES ) / ( NO )
    #   Height Restriction
    #   Fire Fighting
    #   Water Harvesting
    #   Roof-top Solar Power
    #   Effluent Treatment
    #   Garbage Disposal
    #   Earthquake Resistant Structural Design..............etc

Clicking on each item will reveal the relevant " Notification / Regulation " issued by the concerned Ministry
To make the process absolutely fool-proof , the form will insist on an " Electronic Signature " of the applicant

DECLARATION / UNDERTAKING :
" I declare that I have read each and every notification / regulation , listed   in respect of items mentioned above
I further declare that I explicitly agree to abide by these regulations
I am aware that Occupation Certificate will not be granted if my completed project is found to be in violation of any of these notifications / regulations
I will not allow any person / entity to occupy any part of this premises , until and unless , Municipality issues to me , the Occupation Certificate
If Municipality finds any violations , I agree to rectify the same before applying for a fresh Occupation Certificate
If Municipality is not in a position to issue Occupation Certificate due to any
violations which simply cannot be rectified , then I will demolish the said building / project / structure  on my own and before such demolition , refund with interest , payments collected from the buyers
The plot of land is free from any encumbrances / litigations
I am not in default of any loans taken from any bank / individuals
I will not accept any payment in cash , nor make cash payments
I absolve the Municipal Corporation of any liability arising out of non completion of my project 
I agree that my Building Permit Application and my Registration Application details , be made accessible to public on your web site , along with full details of my past / current projects and full details of my balance sheet / bank borrowings  " 

GRANT OF APPROVALS BY MINISTRIES :

As soon as the builder submits the online BUILDING PERMIT APPLICATION , it automatically and instantly , appears on the web sites of ALL the concerned Ministries
The concerned officer of each Ministry , makes APPROVED / REJECTED entries in the application form , from the backend
If rejected , he will provide the reasons
Ministry officers are required to carry out this entry , within 24 hours
As soon as an officer of any Ministry makes entry and SUBMITS , the application forms on web sites of ALL Ministries and web site of the concerned Municipality , get updated simultaneously and instantly , making for MIRROR IMAGES at all times
As soon as any entry is made , a copy gets emailed to the applicant builder
Any " editing " of the application form by the builder , will start the entire process , all over
Applicant builder will be obliged to display the latest emailed form at the site
The database so created on web sites of ALL Ministries - and concerned Municipality - will be searchable State-wise / City-wise

CHANGES  IN  RELEVANT  LAWS :

To speed up any litigation between the parties concerned ( Builder / Buyers / Central & State Govts / Municipality / Bankers etc ) , existing laws may be changed


IMPORTANT :

Every application must be in the open domain and visible to anyone , online and transparently
There should be provision for any visitor of the web site to report any abuse / violation of regulations or any objection to the proposed construction

ADVANTAGES :

If such SELF CERTIFICATION process is implemented , it should be possible for India to beat Singapore , where getting 11 approval takes only 26 days !
It would be ZERO days in our case !
Now couple this with abolition of Corporate Income Tax for Construction Industry for the next 10 years and witness a MIRACLE
Then only it would become possible for achieving the following targets set by different States / Centre , under HOUSING  FOR  ALL:

*  Maharashtra...........  5 lakh      ( By 2020 )
*  Gujarat................... 50 lakh    ( 2013 - 2018 )
*  Centre.................... 220 lakh   ( by 2022 )

Also imagine :

*   Employment it would generate
*   FDI it would bring in
*   Our rank in EASE OF DOING BUSINESS


Need of the hour is :

*   Come out of " Analysis Paralysis "
*   Get rid of historical baggage
*   Break free from the legacy of the past
*   Think " Out of Box "
*   Take risk without worrying about possible failure
*   Make Course-Corrections , as you learn what mistakes got made

-------------------------------------------------------------------------------------

hemen  parekh
04  Jan  2016








POLLUTION SOLUTION , aka " PollSolv "


It is said : Necessity is the Mother of Invention
Let us rephrase :  Essentiality is the Mother of Intervention
This is in response to Odd / Even driving rule being experimented in Delhi from Jan 1 2016
Equally applicable to any other city , threatened by vehicular emission pollution
This solution will be named : PollSolve
It will be in two parts , as follows :
#  VEHICLE BASED DEVICE
All vehicles (existing and future registrations) to be fitted with a GPS locator ( compulsory )
Each of this locator will carry Vehicle Number ( hard-coded )
A software in Delhi Transport Department , will then , be able to track in real time , movement of each vehicle ( 24*7 ) , on several computer screens
If a Odd numbered vehicle is travelling on Even date , it will show up as a RED colored dot on the screen and through linkage with RTO records ,an automatic alert will be issued to the mobile phone of the nearest Traffic Police to catch / stop that vehicle and take that vehicle, off the road !
The owner / driver can take it back after one week of grounding !
This technology is available , commercially and off - the - shelf
Should not take more than 6 months to implement
#  MOBILE BASED APP
Each citizen of Delhi will have to ( compulsorily ) download and install on his smart phone , an App called :  CarPool
He / she will enter following data in the App :
*   Name / Gender /  Aadhar Card No
*   Email Id / Mobile Number / Residence Address / Work-place Address
*   From / To ( in the morning ) / Starting Time of travel
*   From / To ( in the evening ) /  Starting Time of travel
*  If owning a vehicle , then :
    #  Vehicle type : 2 - 3 - 4 wheeler
    #  Fuel type     :  Petrol / Diesel / Electric
    #  Vehicle Capacity : 1 - 2 - 3 - 4 persons (including driver )
    #  Vehicle Number :
    #  Vehicle Registration Date (to compute " Age " of vehicle )
    #  Serial Number of GPS locator fitted on vehicle ( must be unique / Mfrr to take care )
    #  CarPool Number (Unique Serial No allotted by App) : To be entered after joining a Pool
With this data , software will analyze / display , a list containing names / contact info of other citizens ( matched gender-wise ) , travelling on same , approximate " route " and the nearest pick-up points , on Google Map
Citizens will then contact other vehicle-owners and form a CarPool
Then , they will enter their CarPool Number ( as mentioned above )The software will reanalyze / redisplay the list if any entered data gets EDITED later
After compiling data about ONE BILLION actual cumulative travels undertaken by each type of vehicle ( 2-3-4 wheeler ) , BIG DATA ANALYTICS software , will carry out ,
*  Millions of permutations / combinations of " Car Pool Universes " possible
*  Using ( updated version of ) " Karmarkar's Algorithm " , figure out the optimum Car Pool Universe which minimizes the overall pollution level in Delhi    
 *  Calculate for each citizen , the " LEAST POLLUTING ROUTE " based on data compiled from the " Optimum Universe " and  send " Car Pooling Recommendation " to each citizen thru CarPool app
This could be somewhat like " Travelling Salesman Problem " in Linear Programming ( - improved versions could be found in Fuzzy Logic / Neural Network / Artificial Intelligence )
Given the prevalent START-UP wave in India, any number of Indian Start Up companies would be happy to take on this " Two Part " challenge and implement in 6 months . 
It is the least expensive / permanent / replicable solution , suitable for the entire World
All that is required is a POLITICAL WILL and some genuine cooperation between Shri Gopal Rai ( Delhi Govt ) and Shri Nitin Gadkari ( Central Govt )
It is time to offer to the World , an INDIAN ANSWER to vehicular pollution

hemen  parekh


Marol , Mumbai , India


( M ) +91 - 98,67,55,08,08


Sunday, 3 January 2016

BUILDING PERMITS REFORMS


Dear  Change Agents :



Just read about Maharashtra Government announcement re reduction of Building Approvals from 119 to 58

And granting these approvals within 60 days instead of current ONE YEAR  !

Congratulations  !

I hope , someday soon , this will lead to implementation of my following suggestion

When implemented , it will serve as THE  BENCHMARK , for all the other State Governments

with regards,

hemen  parekh / mumbai / (M) 0 - 98,67,55,08,08



----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Wednesday, 4 November 2015

 

SELF CERTIFICATION FOR BUILDERS ?

 

 


In Hindustan Times ( Oct 29 ) , Moushumi Das Gupta writes :

Govt to streamline rules for Construction Projects

Currently , a builder requires as many as 34 kinds of permits from two dozen Ministries, before starting construction

This process takes up to 3 years

Now, Central Govt has initiated a process to streamline the approvals required to ensure that builders get all the construction permits within 60 days

Eg:

*    Built up Area............. Environment Ministry

*    Height Restriction...... .Civil Aviation Ministry

Cabinet Secretary has directed all the Ministries to come out with notifications by end Dec 2015

The Centre has decided to empower Municipalities to grant all construction related approvals , based on these notifications

One would be able to get all approvals from under one roof , which in this case , would be the Municipal Corporation's office

Although a very laudable initiative , I believe there is tremendous scope to further streamline and digitize this approval process, in the nature of

E-Delivery of Services to Construction Industry

Here is how :

*  All builders / developers must register on Municipal Web sites and obtain
   unique BUILDER REGISTRATION NUMBER

*  Builders must fill in online, on web site of concerned Municipality, a form :

    BUILDING  PERMIT  APPLICATION

*  Building Permit Application Form will have a STANDARD FORMAT , into
    which applicant will need to submit exhaustive details re the project

    This will include detailed Floor Plans and Structural Drawings , along with
    names / contact details of Architects / Structural Engineers etc

    The FORM will require slab-casting dates for each slab and the final
    completion date when builder will apply for Occupation Certificate
   
*  The Form will have a section called

    SELF   CERTIFICATION   /  DECLARATION

    Builder would be required to tick YES / NO against each item as shown :

    Does your proposed Building / Structure / Project , satisfy the criteria /
    notifications / regulations , issued by the concerned Ministries in respect
    of :

    #   Built-up Area........... ( YES ) / ( NO )

    #   Height Restriction

    #   Fire Fighting

    #   Water Harvesting

    #   Roof-top Solar Power

    #   Effluent Treatment

    #   Garbage Disposal

    #   Earthquake Resistant Structural Design..............etc



Clicking on each item will reveal the relevant " Notification / Regulation " issued by the concerned Ministry

To make the process absolutely fool-proof , the form will insist on an " Electronic Signature " of the applicant


DECLARATION / UNDERTAKING :


" I declare that I have read each and every notification / regulation , listed   in respect of items mentioned above

I further declare that I explicitly agree to abide by these regulations

I am aware that Occupation Certificate will not be granted if my completed project is found to be in violation of any of these notifications / regulations

I will not allow any person / entity to occupy any part of this premises , until and unless , Municipality issues to me , the Occupation Certificate

If Municipality finds any violations , I agree to rectify the same before applying for a fresh Occupation Certificate

If Municipality is not in a position to issue Occupation Certificate due to any
violations which simply cannot be rectified , then I will demolish the said building / project / structure  on my own and before such demolition , refund with interest , payments collected from the buyers

The plot of land is free from any encumbrances / litigations

I am not in default of any loans taken from any bank / individuals

I will not accept any payment in cash , nor make cash payments

I absolve the Municipal Corporation of any liability arising out of non completion of my project 

I agree that my Building Permit Application and my Registration Application details , be made accessible to public on your web site , along with full details of my past / current projects and full details of my balance sheet / bank borrowings  " 


GRANT OF APPROVALS BY MINISTRIES :


As soon as the builder submits the online BUILDING PERMIT APPLICATION , it automatically and instantly , appears on the web sites of ALL the concerned Ministries

The concerned officer of each Ministry , makes APPROVED / REJECTED entries in the application form , from the backend

If rejected , he will provide the reasons

Ministry officers are required to carry out this entry , within 24 hours

As soon as an officer of any Ministry makes entry and SUBMITS , the application forms on web sites of ALL Ministries and web site of the concerned Municipality , get updated simultaneously and instantly , making for MIRROR IMAGES at all times

As soon as any entry is made , a copy gets emailed to the applicant builder

Any " editing " of the application form by the builder , will start the entire process , all over

Applicant builder will be obliged to display the latest emailed form at the site

The database so created on web sites of ALL Ministries - and concerned Municipality - will be searchable State-wise / City-wise



CHANGES  IN  RELEVANT  LAWS :


To speed up any litigation between the parties concerned ( Builder / Buyers / Central & State Govts / Municipality / Bankers etc ) , existing laws may be changed


IMPORTANT :

Every application must be in the open domain and visible to anyone , online and transparently

There should be provision for any visitor of the web site to report any abuse / violation of regulations or any objection to the proposed construction


ADVANTAGES :


If such SELF CERTIFICATION process is implemented , it should be possible for India to beat Singapore , where getting 11 approval takes only 26 days !

It would be ZERO days in our case !

Now couple this with abolition of Corporate Income Tax for Construction Industry for the next 10 years and witness a MIRACLE

Then only it would become possible for achieving the following targets set by different States / Centre , under HOUSING  FOR  ALL:

*  Maharashtra...........  5 lakh      ( By 2020 )

*  Gujarat................... 50 lakh    ( 2013 - 2018 )

*  Centre.................... 220 lakh   ( by 2022 )


Also imagine :

*   Employment it would generate

*   FDI it would bring in

*   Our rank in EASE OF DOING BUSINESS


Need of the hour is :

*   Come out of " Analysis Paralysis "

*   Get rid of historical baggage

*   Break free from the legacy of the past

*   Think " Out of Box "

*   Take risk without worrying about possible failure

*   Make Course-Corrections , as you learn what mistakes got made

-------------------------------------------------------------------------------------

hemen  parekh


05  Nov  2015




 Hemen Parekh http://img1.blogblog.com/img/icon18_email.gif 


Saturday, 2 January 2016

RE: NEW YEAR’S WISHES From My House To Yours

Dear Geeta,

Thanks for your good wishes , which , we reciprocate

May this new year bring you happiness and health


-  Bharati Masi / Hemen Masa



From: Geeta Vora [mailto:geetavora52@yahoo.com]
Sent: Saturday, January 02, 2016 8:33 AM
To: Geeta Vora
Subject: NEW YEAR’S WISHES From My House To Yours

Namaste,

As the New Year flows in…
Resolve to live life to the fullest…
Resolve to live each day for a new reason…
Resolve to spread smiles and …
Be happy throughout each passing season.

May the New Year be a beginning of
… new hopes,
…..new possibilities and
…..new joys for you.

Thanks for being one of the reasons
I'll have a Happy New Year!"**
Wishing you a fulfilling new Year
Hope High..Dream Big..
Promises New...Joys Afresh

May the Bells of Awesomeness Ring For You in 2016

And may you always remember that the force is
with you. :)
Until next year, be happy, be well and live in joy.
As Always,
Reaching out to make a difference....
Geeta
p.s. Thoughts to Ponder
“An optimist stays up until midnight to see the New Year in.  A pessimist stays up to make sure the old year leaves”… Bill Vaughan
“Cheers to a new year and another chance for us to get it right”…Oprah Winfrey




Geeta S. Vora
website: voraservice.org
phone: 763-780-8837
email:  geetavora52@yahoo.com

Friday, 1 January 2016

STRIKE AVOIDED ?


Dear  Friends :


Just uploaded AMD's contribution :


I was a witness

regards,

hcp

Car Pooling to Solve Pollution Problem


Dear Himanshu ,

I had sent my following suggestion ( my blog ) on your web site

Gargee from your Public Relations Dept wrote , suggesting that I write to you

I reproduce below my blog. There is no " detailed " proposal

Feel free to phone me on (M) 0 - 98,67,55,08,08

regards,

hemen  parekh


PS :

You may like some of my other blogs too , at...........www.hemenparekh.in

Eg :  How to conquer Corruption

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

POLLUTION   SOLUTION , aka " PollSolv "

It is said : Necessity is the Mother of Invention

Let us rephrase :  Essentiality is the Mother of Intervention

This is in response to Odd / Even driving rule being experimented in Delhi from Jan 1 2016

Equally applicable to any other city , threatened by vehicular emission pollution

This solution will be named : PollSolve

It will be in two parts , as follows :


#  VEHICLE BASED DEVICE


All vehicles (existing and future registrations) to be fitted with a GPS locator ( compulsory )

Each of this locator will carry Vehicle Number ( hard-coded )

A software in Delhi Transport Department , will then , be able to track in real time , movement of each vehicle ( 24*7 ) , on several computer screens

If a Odd numbered vehicle is travelling on Even date , it will show up as a RED colored dot on the screen and through linkage with RTO records ,an automatic alert will be issued to the mobile phone of the nearest Traffic Police to catch / stop that vehicle and take that vehicle, off the road !

The owner / driver can take it back after one week of grounding !

This technology is available , commercially and off - the - shelf

Should not take more than 6 months to implement



#  MOBILE BASED APP


Each citizen of Delhi will have to ( compulsorily ) download and install on his smart phone , an App called :  CarPool

He / she will enter following data in the App :

*   Name / Gender /  Aadhar Card No

*   Email Id / Mobile Number / Residence Address / Work-place Address

*   From / To ( in the morning ) / Time of travel

*   From / To ( in the evening ) /  Time of travel

*  If owning a vehicle , then :

    #  Vehicle type : 2 - 3 - 4 wheeler

    #  Fuel type     :  Petrol / Diesel / Electric

    #  Vehicle Capacity : 1 - 2 - 3 - 4 persons ( including driver )

    #  Vehicle Number :

    #  Vehicle Registration Date ( to compute " Age " of vehicle )

    #  Serial Number of GPS locator fitted on vehicle ( must be unique / Mfrr to take care )

     #  CarPool Number (Unique Serial No allotted by App) : To be entered after joining a Pool


CarPool App will not accept the data ,nor get activated ,until Mobile Owner also keeps " ON "
the GPS location feature built into the phone


With this data , software will analyze / display , a list containing names / contact info of other citizens ( matched gender-wise ) , travelling on same , approximate " route " and the nearest pick-up points , on Google Map

Citizens will then contact other vehicle-owners and form a CarPool

Then , they will enter their CarPool Number ( as mentioned above )

The software will reanalyze / redisplay the list if any entered data gets EDITED later

After compiling data about ONE BILLION actual cumulative travels undertaken by each type of vehicle ( 2-3-4 wheeler ) , BIG DATA ANALYTICS software , will carry out ,

*  Millions of permutations / combinations of " Car Pool Universes " possible

*  Using ( updated version of ) " Karmarkar's Algorithm " , figure out the optimum Car Pool
    Universe which minimizes the overall pollution level in Delhi

 *  Calculate for each citizen , the " LEAST POLLUTING ROUTE " based on data compiled
     from the " Optimum Universe " and  send " Car Pooling Recommendation " to each
     citizen thru CarPool app

  

This could be somewhat like " Travelling Salesman Problem " in Linear Programming ( - improved versions could be found in Fuzzy Logic / Neural Network / Artificial Intelligence )

{ " Big data has the potential to make a huge impact on Public Services in India, as it will streamline the decision-making " : Stephen Brobst , Global CTO , Teradata Corporation }

Given the prevalent START-UP wave in India, any number of Indian Start Up companies would be happy to take on this " Two Part " challenge and implement in 6 months .

It is the least expensive / permanent / replicable solution , suitable for the entire World

All that is required is a POLITICAL WILL and some genuine cooperation between Shri Gopal Rai ( Delhi Govt ) and Shri Nitin Gadkari ( Central Govt )

It is time to offer to the World , an INDIAN ANSWER to vehicular pollution

-------------------------------------------------------------------------------------------------------
hemen  parekh
31  Dec  2015